1 | 2007 | BP Atlantis Riser Pull-In System | Testing, Commissioning and Riser Installation | British Petroleum |
2 | 2008 | Armada Perkasa FPSO, Mooring System including Chain Stoppers, Fairleads and Deck Sheaves | Engineering Design, Procurement, Construction, Testing, Commissioning and Mooring Line Installation | Bumi Armada Berhad |
3 | 2009 | Armada Perdana FPSO, Mooring System including Chain Stoppers, Fairleads, Deck Sheaves and Pull-in Winch | Engineering Design, Procurement, Construction, Testing, Commissioning and Mooring Line Installation | Bumi Armada Berhad |
4 | 2009 | Aramada Perdana FPSO Riser Pull-In System | Engineering Design, Procurement, Construction, Testing, Commissioning and Riser Installation | Bumi Armada Berhad |
5 | 2009 | Armada Tua 104 150T A-Frame | Engineering Design, Procurement, Construction, Testing, Installation, and Commissioning | Bumi Armada Berhad |
6 | 2010 | Lewek Falcon 350T A-Frame | Engineering Design, Procurement, Construction, Testing, Installation and Commissioning | EMAS |
7 | 2010 | Shell Gumusut Kakap 100T Reel Transfer System and HPU for Sapura 3000 | Engineering Design, Procurement, Construction and Testing | Sapura Acergy |
8 | 2010 | Shell Gumusut Kakap Hang-Off Platform for Sapura 3000 | Engineering Design, Procurement, Construction and Testing | Sapura Acergy |
9 | 2010 | Shell Gumusut Kakap Hydraulic Wire Pusher for Sapura 3000 | Engineering Design | Sapura Acergy |
10 | 2011 | 120T Spooling Machine with Diesel HPU (Kimspool 8) | Engineering Design, Procurement, Construction, Testing and Commissioning | KTL Offshore |
11 | 2011 | Shell Gumusut Kakap Rack & Pinion Hang-off Platform for Sapura 3000 | Engineering Design, Procurement, Construction and Testing | Sapura Acergy |
12 | 2011 | Shell Gumusut Kakap A&R Roller for Sapura 3000- J-Lay System | Engineering Design, Procurement, Construction and Testing | Sapura Acergy |
13 | 2011 | Shell Gumusut Kakap Personnel Gangway for Sapura 3000 | Engineering Design | Sapura Acergy |
14 | 2011 | 30T Pipe Lay Tensioner, A&R Winch and HPU | Engineering Design, Procurement, Construction and Testing | PT Onasis |
15 | 2011 | Motion Compensated Workover Tower | Engineering Design, Procurement, Construction and Testing | Murphy Oil |
16 | 2012 | Shell Gumusut Kakap Pig Launcher | Procurement, Construction and Testing | Sapura Acergy |
17 | 2012 | Shell Gumusut Kakap Load Handling Equipment for J-Lay Pipe Coating Station for Sapura 3000 | Engineering Design, Procurement, Construction and Testing | Sapura Acergy |
19 | 2012 | Gumusut Kakap Riser Pull-In Heads | Engineering Analysis | Sapura Acergy |
20 | 2012 | FPSO Cendor Mooring System including Chain Stoppers, Fairleads and deck sheaves | Engineering Design, Procurement, Construction and Testing | MISC |
21 | 2012 | 100T Crane Modification | Engineering Design, Procurement, Construction and Testing | Allied Marine & Equipment |
22 | 2012 | 2T Man-Riding Crane | Engineering Design, Procurement, Construction and Testing | ASL Shipyard |
23 | 2012 | Shell Gumusut Kakap Riser Pull Head Load Test Flanges | Engineering Design, Procurement, Construction and Testing | Sapura Acergy |
18 | 2013 | 5T Constant Tension Winch | Engineering Design, Procurement, Construction and Testing | CAZ |
24 | 2013 | Surface Mooring Connection Tool | Engineering Design, Procurement, Construction and Testing | Technip |
25 | 2013 | 30T Riser Pull-In Winch and Turndown Sheave | Engineering Design, Procurement, Construction and Testing | MISC |
26 | 2013 | Personnel Gangway | Refurbishment | EMAS |
27 | 2013 | Rio Tinto Train Car Positioner and HPU | Engineering Design, Procurement, Construction and Testing | ARK |
28 | 2013 | Gumusut Kakap Overboarding Roller for Sapura 3000 A&R Winch | Engineering Design, Procurement, Construction and Testing | Sapura Acergy |
29 | 2013 | Streamer Winch and HPU, 2 sets | Engineering Design, Procurement, Construction and Testing | Piasau Slipways |
30 | 2013 | PDVSA Chain Stoppers and Fairleads with Load Monitoring | Engineering Design, Procurement, Construction and Testing | Technip |
31 | 2013 | Gumusut Kakap Riser Pull-In Contingency Analysis | Engineering Analysis | Sapura Acergy |
32 | 2014 | Constant Tension Hose Winch and HPU | Engineering Design, Procurement, Construction and Testing | Armada Rig Builders |
33 | 2014 | Gorgon Subsea Equipment Seafastening | Engineering Design | Subsea 7 |
34 | 2014 | Cluster 7 FPSO Deck Sheaves for Mooring Pull-In | Engineering Design, Procurement, Construction and Testing | Bumi Armada Berhad |
35 | 2014 | Hawser Winch and HPU, 2 sets | Engineering Design, Procurement, Construction and Testing | Lundin |
36 | 2014 | Armada JPC Launch and Recovery System | Engineering Design, Procurement, Construction and Testing | Armada Rig Builders |
37 | 2015 | 40T Box Boom Crane | Engineering Design | Hoang Long Joint Operating Company |
38 | 2015 | 150T Lattice Boom Crane | Engineering Design | Koastal Industries Pte Ltd |
39 | 2015 | Shell Malakai Riser Pull-In System | Refurbishment, Testing and Re-certification | Technip |
40 | 2015 | JSPL Mooring Winch and Underwater Fairlead | Engineering Design | Jurong Shipyard Pte Ltd |
41 | 2015 | TYM Anchor Handling Winch and Fairlead | Engineering Design | Vietsovpetro |
42 | 2015 | Thunder Horse Mooring Chain Jacks Replacement | Engineering Design | British Petroleum |
43 | 2015 | Rig Skidding System | Engineering Design, Procurement, Construction and Testing | EMS |
44 | 2015 | Badamyar Pipeline Installation Aids | Fabrication | Sapura Acergy |
45 | 2015 | Badamyar Installation Aids Seafastening | Engineering Design | Sapura Acergy |
46 | 2015 | Badamyar Overboarding Chute | Engineering Design, Procurement, Construction and Testing | Sapura Acergy |
47 | 2016 | 2700HP Diesel HPU | Engineering and Testing | Versabar |
48 | 2016 | Seawater Distribution Manifold with Flow Measurement | Engineering | Versabar |
49 | 2016 | Vessel Lifting System, Screw Jacks and HPU | Engineering and Testing | Versabar |
50 | 2017 | Rig Skidding System and Sea-fixing Clamps | Engineering | Versabar |
51 | 2017 | BOP Testing Stand | Engineering | C Automation |
52 | 2017 | 100T Active Heave Comp Winch System | Engineering, Testing, Installation and Commissioning | Versabar |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |
| | | | |